What is known

On November 20, Seojeon disclosed a KRW 7,493,413,000 contract, excluding VAT, with Hyundai Engineering & Construction to manufacture, install and supply switchgear and distribution boards through August 21, 2028. No advance payment is provided; payments are monthly, within 60 days of receipt of the deliverables. Production is in-house; the value equals 11% of the supplier’s 2025 separate-statement revenue.

Our analysis

Financing starts before the payment clock

Sales sees future revenue in the order; production sees an assembly schedule and a need for components. Finance needs to establish how much of the supplier’s own cash will be committed before settlement. These views should meet before volume and timing are promised: an order that looks profitable can still create a cash shortage.

A payment period starting on receipt of equipment covers only part of the wait. Materials, labour and freight may be paid for well before delivery. The calculation therefore begins with dated cash outflows and ends with receipts for each shipment. This identifies the additional financing the particular order requires.

Which event starts the clock?

A supplier’s own contract needs a defined starting event: receipt of goods, a signed document, quality inspection, completed installation or another agreed milestone. Seojeon’s published reference to receipt of deliverables cannot automatically be replaced by an invoice date or technical acceptance.

Monthly payments likewise do not justify simply adding a month to the 60 days. A calendar needs the payment-cycle rules and receipt dates for the shipments. Clarification affects pricing: apparently shared wording can produce different cash outcomes if the parties use different starting events.

The cost of waiting

Consider an invented shipment priced at 120 monetary units. For simplicity, all 100 units of production expenditure are paid on day 0. Delivery occurs on day 45; full payment arrives 60 days later, on day 105. At an assumed annual funding cost of 18%, simple financing cost is 100 × 18% × 105 / 365 = 5.18. These are parameters of our model, not the Korean contract.

Illustrative termsSupplier cash tied upFinal settlementSimple financing cost
No advance; payment 60 days after delivery100Day 1055.18
No advance; payment 30 days after delivery100Day 753.70
Advance of 30 on day 0; remaining 90 on day 10570Day 1053.62

The third scenario keeps price at 120 and expenditure at 100. An advance of 30 reduces the supplier’s own cash committed until settlement to 70. Actual expenditure is usually spread over time; component-supplier credit, taxes, fees and security also affect the calculation. The table illustrates a mechanism to recalculate using the dates of a particular transaction.

In this model, moving from 60 to 30 days after delivery reduces financing cost by 1.48 monetary units. That gives price and payment negotiations a specific figure to discuss, all else equal. We have not included any additional value from releasing capacity or starting another shipment sooner.

What remains of the price

The 20-unit gap between price and direct expenditure has to cover financing, overhead, warranty and other costs. Sales can compare alternatives through the amount remaining after those costs for the same work. An early-payment discount then gains an economic basis: it is weighed against released cash rather than assessed solely as lost revenue.

The next shipment adds another layer. If production starts before the previous shipment is paid for, cash troughs overlap. A contract’s share of annual revenue helps establish its scale; a combined shipment schedule reveals peak cash requirements. Sales growth may reach that limit before reaching the plant’s physical capacity.

What the buyer gains from deferral

Deferred payment gives a buyer time to use or inspect equipment before paying. Its cost may return through price, available capacity or the bidder pool. A technically suitable manufacturer may decline volume it cannot finance. Negotiation can address shipment size, payment timing and payments against verifiable milestones together with performance controls.

An advance transfers part of the non-performance risk to the buyer; a milestone payment needs evidence of completed work. Alternatives should be assessed alongside security, rights to the work and dispute arrangements. Payment timing becomes part of supplier selection: the buyer evaluates both technical delivery capability and the financial ability to sustain the terms.

The decision before the next order

Before promising more volume, establish the maximum cash committed at one time, including existing obligations. If available financing falls short, negotiation needs to change a specific variable: shipment size, advance, timing or price. This connects the sales plan with an achievable production schedule. The four supporting records for that discussion are examined separately in the Buyer’s Desk section.

Limits of the evidence

The disclosure establishes published terms, not performance. Shipment schedules, acceptance details, margins, funding costs, actual receipts and payment security are not disclosed. Contract value and timing may change under its terms.

The calculations are editorial illustrations. They neither estimate Seojeon’s economics nor predict its profit.

Primary sources